Home
Construction Planning
Construction Scheduling
Critical Path Method
Project Control
Earned Value
NEC 3
NEC3 Clause 30
NEC3 Clause 31
NEC3 Clause 32
NEC3 Clause 34-35
NEC3 Clause36
Time Risk Allowance
Check List for compliance
Delay analysis records
Record Keeping
PERT
Disclaimer

Critical Path Example: Manually Calculating the Critical Path

The critical path example consists of demonstrating the forward and backward pass.

The Forward Pass

Calculates ES and EF times

Computes early event time for each node

Move left to right on the diagram below

1. Take the preceding activity early event time and add the duration

2. If more than one activity precedes it then the largest value is recorded

3. Write down trial values

Note the first node always has an early event time of 0

Your example should now look like this:

The Backward Pass

Calculates LS and LF times

Computes the late event time for each node

From right to left

1. Take the preceding Late event time and subtract duration

2. If more than one activity precedes it then the smallest value is recorded

3. Write down trial values

Your example should now look like this: Determine Critical Activities

Activities are critical when:

1.Early Event Time & Late Event Time are the same

2.ES and LS & EF and LF time are the same

Applying these rules to our example the Critical Path is as follows:

Return from Critical Path Example to Home Page Return from Critical Path Example to Critical Path Explained


footer for Critical Path Example page